Cementa AB

Cementa AB, Slite, Sweden

Turn key delivery of terminal for intake, storing and weighing of flygaska at Cementa´s production facilities, Slite. The project comprises engineering, manufacturing, assembly and test run of equipment designed for the intake of flygaska from ships, storage of flygaska and cement i two storage tanks and dosage of the material into grinders.

The installation includes:

  • – Intake from quay to separator with capacity 250 tonnes/h.
  • – Separator with filter, capacity 18,000 m3/h.
  • – Transportation to storage tanks via Trelleborg Scirocco-tubes and bucket elevator from storage tanks to weighing equipment.
  • – Dosage from weighing equipment to bucket elevator before grinding.
    Dosage station comprises cellfeeder, Corolis weighing equipment and Trelleborg Scirocco-tubes.
  • – Electrical equipment and installation.

Site preparations have taken place during spring 2012.
Assembly will start during autumn 2012 and start up is scheduled to Q2 2013.
After start up we will present further project details with technical specifications.